Cisco 300-415 (Implementing Cisco SD-WAN Solutions (ENSDWI)) Practice Test 13

Question 120

A new edge reports a DTLS handshake timeout, but a ping succeeds to Controller. What should be investigated?

  1. Control protocol ports, stateful firewall behavior and MTU or packet handling
  2. Only the branch's configured OSPF redistribution metric
  3. Only the VLAN name of an unrelated wireless SSID
  4. Only the AppQoE DRE dictionary size

Explanation

Correct Answer

A:

ICMP reachability proves only a limited path. DTLS/TLS may use different transport behavior and can fail if required packets or responses are filtered.

Incorrect Answers

B:

A service-side route cost is not the first reason a secure control handshake times out over reachable underlay transport.

C:

SSID labels do not allow blocked control packets through the WAN firewall.

D:

Data redundancy elimination applies to traffic optimization, not initial DTLS/TLS signaling to controllers.

Question 121

A technician sees 'certificate revoked' or similar rejection during a new control connection. Which response is appropriate?

  1. Enable NAT on every service-facing LAN interface
  2. Investigate certificate status and authorize a valid replacement credential
  3. Configure OMP to prefer the rejected node's routes
  4. Raise BFD failure detection intervals to several minutes

Explanation

Correct Answer

B:

Revocation is a security decision that prevents use of a compromised or invalid identity. Restoring trust requires proper issuance and list updates, not disabling checks.

Incorrect Answers

A:

NAT on local user networks does not restore cryptographic validity to a revoked control certificate.

C:

Route policy cannot make a revoked credential pass mutual authentication before an OMP session exists.

D:

Data-path timers do not change PKI revocation validation during control connection establishment.

Question 122

All edges registered in one office fail Controller connections, while remote offices work. Which scope-based diagnostic is most efficient?

  1. Compare the affected site's underlay routes, DNS resolution, firewall and NAT with a healthy site
  2. Disable data-plane IPsec encryption across all branches
  3. Delete the enterprise-wide authorized serial file
  4. Redeploy every Controller because any one office failed

Explanation

Correct Answer

A:

A site-local failure domain suggests differences in transport path or configuration. This narrows the issue before making changes to healthy central controllers.

Incorrect Answers

B:

A localized control reachability problem does not justify weakening the overlay encryption design.

C:

Removing valid authorizations would likely extend onboarding failures to healthy locations.

D:

Working sites indicate central services are at least partly functional; wholesale redeployment can add risk without locating the local cause.

Question 123

A site-specific control policy accidentally suppresses remote routes, but OMP adjacency remains up. Which diagnostic distinction matters?

  1. Established peer status does not imply all prefixes are advertised or accepted
  2. The only repair is to reset all controller certificates
  3. A healthy OMP peer guarantees every remote prefix is installed
  4. No advertised routes proves the transport interface has no IP address

Explanation

Correct Answer

A:

Control policies may filter OMP updates independently of adjacency health. Inspect received, advertised and installed routes together with applied site policy.

Incorrect Answers

B:

PKI renewal is unrelated to the selective disappearance of routes under an otherwise healthy OMP peer.

C:

Route filtering, VPN scoping and TLOC resolution can legitimately prevent specific route installation even with an active session.

D:

An established control connection already indicates that some underlay connectivity exists.

Question 124

A WAN Edge control connection repeatedly resets after a software upgrade. What evidence should be gathered first?

  1. Only a screenshot of the last SaaS score
  2. Only the branch's inventory barcode
  3. Control failure reason codes, software compatibility and secure transport logs
  4. Only the Controller's cosmetic hostname text

Explanation

Correct Answer

C:

A post-upgrade change could affect interoperability, certificate handling or network behavior. Correlate exact versions and errors before rollback or configuration edits.

Incorrect Answers

A:

SaaS performance data does not directly diagnose a control component rejecting or resetting authenticated sessions.

B:

Asset tags identify hardware but reveal little about a control protocol reset following a software-version change.

D:

Hostnames aid identification, but the upgrade-related errors and protocol compatibility are more actionable for repeated resets.

Question 125

A business wants continuity during controller maintenance. Which maintenance sequence is least disruptive?

  1. Purge all Controller authorized device lists before a rolling change
  2. Disable the WAN Edge underlay first, then upgrade controllers
  3. Shut down every Controller simultaneously to make versions match
  4. Verify redundant peers are up, maintain one failure domain at a time, and confirm reconvergence

Explanation

Correct Answer

D:

Maintaining live alternative control sessions reduces the chance that planned work removes all OMP reachability. Capacity and rollback readiness still matter.

Incorrect Answers

A:

Erasing authorization can cause valid routers to fail reconnection during and after the maintenance window.

B:

Removing transport connectivity prevents sites from reaching surviving control components and worsens maintenance impact.

C:

This deliberately removes control-plane redundancy and can disrupt policy distribution or route refresh during the window.

Question 126

A company plans to host controllers on a private virtualization cluster. Which two network considerations apply? Choose TWO.

  1. Identical per-device system IP values to simplify routing
  2. Reachable transport endpoints for WAN Edge control sessions
  3. All control traffic encapsulated as branch LAN OSPF packets
  4. Resilient management and intercomponent connectivity
  5. Guaranteed service VPN access for every internet user

Explanation

Correct Answers

B:

The controller VM's transport-side network must be routable from intended edge underlays, directly or through supported NAT and firewall designs.

D:

Manager, Validator and Controller services need reliable administrative and required component paths for operation, certificate distribution and maintenance.

Incorrect Answers

A:

Device identities must be distinguishable; duplicating system IPs would undermine control-plane correctness.

C:

Secure SD-WAN signaling uses its defined transport protocols, not arbitrary substitution by service-side OSPF.

E:

Unrestricted service-network exposure is neither a controller deployment prerequisite nor a secure practice.

Question 127

A company uses cloud-hosted controllers but a self-managed on-prem Manager integration. What operational assumption should be avoided?

  1. Assuming all components share one failure domain or reachability method
  2. Considering latency and redundancy of the chosen deployment model
  3. Using documented secure connectivity between components
  4. Acknowledging separate management and control responsibilities

Explanation

Correct Answer

A:

Hybrid control deployments require explicit planning for management, orchestration and controller endpoint access. Provider hosting does not magically make private management paths public.

Incorrect Answers

B:

Placement and path diversity matter for stable operations and do not conflict with hybrid hosting.

C:

Component-level transport and trust requirements remain necessary regardless of where VMs are hosted.

D:

Maintaining distinct roles improves troubleshooting and is consistent with the SD-WAN architecture.

Question 128

A new Manager VM is installed and can be reached over its management network. What must still be planned before onboarding remote edges?

  1. Only configuring Cloud OnRamp for SaaS application probe targets
  2. Trust configuration, component reachability, inventory and device configuration workflows
  3. Turning Manager into the exclusive internet transit device
  4. Disabling all controller control sessions until after service traffic starts

Explanation

Correct Answer

B:

Manager installation is only one stage. Validator/Controller connectivity, authorization lists and intended edge settings must be ready before scalable provisioning.

Incorrect Answers

A:

SaaS monitoring provides application egress insight but does not prepare Controller trust, device authorization, or installation of initial branch configurations.

C:

Management software is not the edge router that carries ordinary encrypted branch traffic.

D:

Fabric route distribution and secure introduction are prerequisites for normal overlay service forwarding, not optional later tasks.

Question 129

The organization rotates from a Cisco-signed to an enterprise-signed certificate model. What is a major transition risk?

  1. Service VPN addresses must be changed to public IPs
  2. OMP ceases to support TLOC route advertisements under enterprise PKI
  3. Participants without the new trusted CA chain can reject freshly issued credentials
  4. All BFD sessions automatically measure zero latency afterward

Explanation

Correct Answer

C:

Trust-anchor distribution and certificate changes must be sequenced across components and WAN Edges. A partial migration can partition control authentication.

Incorrect Answers

A:

Certificate issuer changes do not inherently require renumbering production service networks.

B:

The route protocol can function with correctly authenticated enterprise certificates; switching issuers is not a reason to remove TLOCs.

D:

PKI issuer selection does not eliminate WAN delay or packet loss measured on established data tunnels.

Question 130

A remote branch can reach the Validator but not the Controller hostname supplied during discovery. Which check is next?

  1. Resolve the advertised Controller hostname and test routed reachability from VPN 0
  2. Enable packet duplication on all branch applications
  3. Change every local LAN subnet mask
  4. Delete the branch's authorized certificate from Manager

Explanation

Correct Answer

A:

Discovery success does not guarantee that controller-specific DNS or transport paths work. Confirm the endpoint and forwarding next hop before altering overlay routing policy.

Incorrect Answers

B:

A data resilience action will not repair a missing DNS record or underlay path for secure controller traffic.

C:

Branch service-address changes could create new issues without fixing controller endpoint resolution or transport reachability.

D:

Revoking a permitted device is counterproductive when the immediate symptom is hostname or network reachability.

Implementing Cisco SD-WAN Solutions (ENSDWI) (300-415) Practice Tests